Question

KLC_1 on Thu, 18 Aug 2016 23:43:31


Hi,

I am creating a VSO instance for a program that has more than 10 workstreams. Each workstream needs to be in VSO. My question is, based on the below requirements, what is the best set-up of VSO? Should each workstream be an area or a team? Or is there another set-up with VSO that would be better?

Requirements include:

-Being able to see each workstream separately 

-Being able to have separate iterations/sprints

-Being able to give admin access to specific workstreams

-Being able to move features and/or stories between the different workstreams

Thank you for your help!


Sponsored



Replies

Sunil Hurkadli on Fri, 19 Aug 2016 15:37:47


Greetings,

Yes, this is possible, please check the below link which gives you more detailed information on handling multiple Teams.

https://www.visualstudio.com/docs/work/scale/multiple-teams

Hope this helps. Please let us know if you need anything else.

Regards,

KLC_1 on Fri, 19 Aug 2016 21:47:03


Thanks so much, this was what I needed.